While preparing the status report for stakeholders,the project manager discovers a negative
cost variance for a project where 10 percent of their work has been completed.What should the project manager do prior to meeting with the stakeholders?
A.Forecast the estimate at completion(EAC).
B.Initiate charge control procedures.
C.Put the project on hold until a response strategy is determined.
D.Use the contingency reserve.
1.在为相关方准备状态报告时,项目经理发现一成本偏差为负数,该项目 10%的工作己经完成,在与相关方开会之前,项目经理应该怎么做?
A.预测完工估算(EAC).
B.启动变更控制程序
C.搁置项目直到确定应对策略
D.使用应急储备